1 | EGYPT – NORTH BAHARIYA PETROCHEMICAL Co./ TYCO THERMAL CONTROLS, BELGIUM Design, supply, installation & commissioning of Instrumentation for Gas Separators. | TYCO | 2007 | Completed |
2 | TYCO THERMAL CONTROLS, BELGIUM Design, Supply, Installation & Commissioning of PLC & SCADA and Instrumentation for GAS Separators | TYCO | 2007 | Completed |
3 | SUDAN – PETRODAR OPERATING Co./ TYCO THERMAL CONTROLS, BELGIUM Design, supply, installation & commissioning of Instrumentation for Chemicals injection skids. | TYCO | 2008 | Completed |
4 | EGYPT – QARUN PETROCHEMICALS LTD. / TYCO THERMAL CONTROLS, BELGIUM *Design, supply, installation & commissioning of Instrumentation for Chemical injection skids. *Design, supply, installation & commissioning of Instrumentation for Test separator skids. |
TYCO | 2008 | Completed |
5 | KSS Engineering (I) Limited- KSS Kazakhstan Supervision of Installation & Commissioning of Instrumentation & Electrical Systems for a Gas Compressor Station & Pipeline Network- Period of Deputation of 3 Engineers- 2 Years | - | 2012 | Completed |
6 | Unilever Srilanka Limited, Srilanka Supply, Installation & Commissioning of Automation & Instrumentation for CLS Project | Unilever | 2013 | Completed |
7 | KUSILE Power plant South Africa Planning, Supervision, Erection and Commissioning of 6x850MW Thermal Power Project | - | 2017 | Completed |
8 | Unilever Srilanka Limited- Srilanka Supply, Installation & Commissioning of Instrumentation for PC REBUILD Project. | - | 2017 | Completed |
9 | Automation of Vibration Monitoring System for Dedusting Station, Abu Dhabi | - | 2019 | Completed |
10 | DGPC- Bhutan, Kurichhu Hydropower Plant, Supply and Delivery of Radar Type Water Level Sensor and Gate Position Sensor with Complete Accessories Including Installation, Testing and Commissioning | - | 2019 | Completed |
11 | Renovation &Modernisation of C&I Package Al-Mussaib oil Fire Power Station 4x300 MW- IRAQ ELECTRICITY. | Siemens Germany | 2020 | Completed |
12 | TANZANIA Extension of Lake Victoria Pipeline to Tabora, Lgunga & Nzega Towns Package-I, Tanzania | 2021 | Completed | |
13 | Unilever Nepal Limited, Nepal Electrical & Instrumentation Supply and Installation Services | Unilever | 2022 | Running |
14 | Unilever Bangladesh Limited, Bangladesh Instruments Installation Job, Milder Preservative Project | Unilever | 2022 | Running |